Case

Which case won?

casea
The case for the land owner
  • The developer had indicated that he would have development approval within six months of us entering into the contract in April 2015. My initial intention was to sell my land within six months.
  • After it became clear that the developer would not be able to call the option in that time, in November 2015 we negotiated a further six-month term, and this was reflected in a deed of variation. This meant that the developer had over a year from the date of us entering into the original agreement to call the option. It has now been three and a half years and the option has still not been called.
  • The developer has no current development application on foot with the council. This shows that he is not making any reasonable attempts to complete the contract.
  • The developer does not have a caveatable interest in my land, because in my view, the contract came to an end six months after the deed of variation was negotiated. His caveat is preventing me from being able to deal with my land and the court should order that the caveat be withdrawn.
caseb
The case for the developer
  • While it was my intention to try to complete the transaction within six months, this was not included as a term of the contract, because although I could try to obtain development approval, I could not guarantee that it would be granted within six months.
  • I did make an application to the council for development approval within the six-month period. However, the application was refused because the council had some concerns regarding asbestos contamination of the land. I was not previously aware of the extent of this contamination, nor the impact that the contamination would have on obtaining the development approval.
  • The council required that certain works be done regarding the contamination before it would consider granting development approval. I obtained a quote for undertaking the contamination works and found it to be quite costly. Procuring the finance required to fund the contamination works would take some time.
  • I am ready, willing and able to perform the contract. The land owner should not be able to end the contract because I have not breached a term of the contract. The relevant term of the contract is that I must call the option within 30 days of development approval being granted. Since development approval has not been granted yet, I am not in breach of the contract.

So, which case won?

Cast your judgment below to find out
Case A Case B

Case A won. You were right!

How people voted
case a70%
case b30%

Expert commentary on the court's decision

Zohra Ali
Zohra AliSenior Associate
“The court found that because the developer did not currently have a development application on foot and had not taken any steps to remedy the contamination identified by the council, the developer could not be considered to be ready, willing and able to perform the contract.”

Declaration of interest: Stacks Champion acted for the landowner in the proceedings described in this article.
Court finds in favour of land owner

In Rosengreen v Saadie Group Pty Ltd [2018] NSWSC 1068, the court ruled in favour of the land owner, Mr Rosengreen, in a claim that looked at whether the passing of time could cause the contract to come to an end.

The court determined that while the relevant contract term stated that the developer had 30 days from the date on which development approval was granted to call the option, it was clear that the intention of the parties was that the development approval would be obtained within six months of the contract being entered into.

The court found that for the developer’s argument to be successful, the court would have to find that the contract was not time bound. The court determined that it was clear from the evidence that this was not the case and that the landowner had an expectation that the contract would be performed within six to 12 months.

Further, the court found that because the developer did not currently have a development application on foot and had not taken any steps to remedy the contamination identified by the council, the developer could not be ready, willing and able to perform the contract.

Option agreements should clearly specify an expiry date

Developers must be very careful in stipulating contract terms for prospective land purchases. Having a clear, express term that indicates the final date by which the developer must call the option will alleviate any doubts as to the end date of the contract.

Stipulating time periods based on the anticipation of a certain milestone being reached can result in ambiguity as to the true expiry date of the contract. It can lead to a contract becoming frustrated due to the impossibility of it being performed, or alternatively, as occurred in this case, being terminated due to the passing of time.

NOTICE: This article is accurate as at the time of publication and does not constitute legal advice. Please see our legal notices page for more information. Information related to coronavirus can be outdated very quickly.

Latest from Stacks

chat button

Fill out this form and one of our local law professionals will be in contact

By submitting this form you agree to the terms of our Privacy policy